Jay Fergusonjay@deepcreekvacations.com301-501-0420
Menu

Ad Valorem Tax Rates To Increase For Some Water, Sewer Customers

May. 23, 2013

Director Linda Lindsey, Garrett County Department of Public Utilities, on Tuesday presented the county commissioners with her calculated ad valorem tax rates for water and sewer service in the Garrett County Sanitary District for fiscal year 2014.

Rates for Bloomington water, Chestnut Ridge sewer, Deer Park water and sewer, Friendsvile water and sewer, Keysers Ridge water, Meadow Mountain sewer, and Mtn. Lake Park/Loch Lynn sewer customers will remain at their current rates.

republican_logo

Lindsey plans to increase the Deep Creek Lake sewer ad valorem tax rate from $.06 to $.07.

“The ad valorem tax rate is based [in part] on the assessed valuation of the properties within the service area boundaries,” she explained about the increased. “There was a decrease in some of the assessments, and then an additional cost for the loan refinancing that we recently conducted. We consolidated all of the [Deep Creek Lake] Sanitary District’s debt.”

The Jennings sewer rate will increase from $.13 to $0.22.

“That’s due to additional expenses for constructing the main line sewage pump station on the conveyance line from Jennings to the Chestnut Ridge area,” Lindsey explained. “That money – $1,000 – was borrowed to do that.”

McHenry water customers will see a $.01 increase.

“It goes from $.04 to $.05, and that is due to the loan refinancing of the previous USDA loan and M&T construction loan,” the director said.

The Mtn. Lake Park/Loch Lynn water rate will go from $.02 to $.05.

“That [increase] is based on the debt incurred for the new the water treatment plant, new 500,000 gallon water storage tank, the new wells for the new water source, and distribution system rehabilitation that’s been undertaken,” Lindsey said.

The rate for the new Thayerville water system will be $.20.

“That’s based on the new construction of the system that’s ongoing at this time,” the director said.

More here.

Thayerville water project progressing

Elaine Blaisdell Cumberland Times-News

OAKLAND — Work on water storage tanks for the $8.22 million Thayerville water system is 99 percent complete, according to Linda Lindsey, director of the Garrett County department of public utilities.

The distribution system is 50 percent complete and Frank Arnold Contractors has completed 45 percent of the water treatment plant/booster station, Lindsey reported during the county commission meeting Tuesday.

The project is separated into three construction contracts — the distribution system (contract 1), the water storage tanks (contract 2) and the water treatment plant/booster station (contract 2A).

Dutchland Inc. has constructed two concrete water tanks, a 1,013,150-gallon tank and a 156,000-gallon tank, according to Lindsey.

“They are both basically complete. The contractor just needs to install the air breaks on both tank overflows,” said Lindsey. “We will do a final inspection and that portion of the project will be complete.”

Piping for the distribution system has been installed in the Quarry, Fox Den, Leo Friend roads and the Overlook development areas, according to Lindsey.

“The contractor (Excavating Associates) is currently completing the main line and service laterals in the Mountain Side development,” said Lindsey. “They are planning on continuing to work as long as weather permits. The contractor anticipates working on the Glendale Road and U.S. Route 219 south segments after the winter shutdown. Basically, those areas require the availability of paving and we can’t work within the state roadway when there is any chance of a snow emergency.”

The distribution system project will likely be started back up in early April, according to Lindsey.

Dutchland has set a chlorine contact tank in the water treatment plant and the pipe work has been started.

“They are hoping to get block foundation up this week while the weather permits,” said Lindsey.

In 2009, the county commissioners approved the Thayerville water project and in 2010 entered into an agreement with RK&K Engineering for the work. The project was pending on 33 easements that were required from private property owners.

Contact Elaine Blaisdell at eblaisdell@times-news.com.